Rio Rancho Multi-Generational Recreation Center: Costs, Phases and Funding

The corner of Northern and Rockaway boulevards has already been used for more than one thing. The building there was Ernest Stapleton Elementary until the school got a new site to the west. Shining Stars preschool moved into the old building in 2005 and stayed until its own new building opened in August 2021, according to the Rio Rancho Observer.

The City of Rio Rancho now owns those 13 acres at 4477 9th Ave. NE and plans to put a Multi-Generational Recreation Center there. The preliminary estimate for the whole project is $76 million, split into two phases. Phase 1 is the gym. Most of what families and court players would use, including the pickleball courts and climbing space, is in Phase 2, which is the furthest from having money.

What each phase holds

The city's project handbill and reporting from The Paper, published on nm.news, split the project like this:

Phase 1 Phase 2
Building size 49,140 sq ft 33,534 sq ft
Estimated cost $42,582,750 $33,781,100
Indoors Reception and facility office, multisport gymnasium, restrooms and changing rooms, equipment storage Flexible space for gymnastics and climbing, fitness and cardio, multipurpose rooms, a stage, a café, office space
Outdoors Basketball courts, walking trails, parking Tennis and pickleball courts, playgrounds, an agility course

Together the two phases come to 82,674 square feet, with a combined preliminary estimate of $76,363,850.

Look at what falls on each side of the line. Phase 1 has the gym, outdoor basketball, trails and parking. The tennis and pickleball courts, the climbing and gymnastics space, the fitness room, the playgrounds and the café are all in Phase 2.

The handbill says splitting the project lets the city "take a fiscally responsible approach to delivering these amenities while creating a strong foundation for continued community investment and growth." In practice, the first $42.6 million pays for a gym building with courts and trails outside. The second $33.8 million pays for the rest.

How far along it is

The handbill also lays out the city's timeline so far:

  1. 2023 to 2025: The city adopted the project into its 2023–2028 Strategic Plan and secured the 9th Avenue site. It completed a site and needs assessment "based on historic citizen feedback" and developed a conceptual design.
  2. 2025 to 2026: The Governing Body, meaning the mayor and city council, saw the design and cost estimates and told staff to take a phased, cost-effective approach. Staff then showed the phased plans to citizen boards and at a public town hall.
  3. Next: Public feedback goes into construction documents for both phases. Phase 1 design is listed as underway in 2027, and The Paper reports it should wrap up in early 2028.

The handbill states the last condition plainly:

Phase 1 construction can begin once design is complete and funding is secured.

As of The Paper's October 28 report, no money had been identified to build it. The report's "by the numbers" box lists zero dollars for construction and says the estimates grow about 4% for each year past 2026.

The price compared with Rio Rancho's usual park budget

Rio Rancho voters decide on general obligation bonds, which are city borrowing approved at the ballot box. The bond questions have usually come as a set: roads, public safety, and "quality-of-life" facilities such as parks and libraries. City staff described this regular bond cycle as dating to 2016, according to 2023 advisory board minutes. The parks and library share has been small:

  • 2024 ballot: The quality-of-life question was set at $1.2 million out of a $16 million package. The Rio Rancho Observer reported that the projects included replacing the basketball court at Star Heights Park, a new playground, surfacing and shade structure at Vista Sandia Park, and library materials and equipment.
  • March 2026 ballot: Voters approved three questions totaling $18 million, according to The Paper. That was about $12.4 million for roads, $4.4 million for public safety and facilities, and $1.2 million for quality-of-life facility improvements.

Put those next to the rec center. Phase 1 alone, at $42.6 million, costs more than twice the entire $18 million package voters approved in March 2026. At 4%, the Phase 1 estimate grows by roughly $1.7 million in a year, which is more than a full quality-of-life bond has carried in either recent round. On the combined estimate, a year of delay adds about $3 million.

That arithmetic is why the phasing matters for the Phase 2 amenities. The court and climbing space follow a $42.6 million building that has a design schedule and no construction money. And Phase 2's $33.8 million estimate keeps growing while it waits.

What residents would get first

If Phase 1 gets built as drawn, the first things to open at Northern and Rockaway would be a multisport gym, outdoor basketball courts, walking trails and a parking lot. That's a real addition to the north side of the city, though a narrower one than the phrase "multi-generational recreation center" suggests. The Phase 2 pieces are the ones that would make it multi-generational: gymnastics and climbing, a fitness room, multipurpose rooms, a stage, and a café to sit in between activities. Tennis, pickleball, playgrounds and an agility course are in Phase 2 as well.

The drawings are still conceptual, and the handbill says public feedback will shape the construction documents for both phases. That makes this the stage where residents' comments on what goes in each phase can still affect the plans.

Where to see the designs

The city scheduled a drop-in community open house for Monday, November 9, at 6 p.m. at Loma Colorado Library, 755 Loma Colorado Blvd. NE. The plan was conceptual designs and information displays, a chance to leave feedback, and no formal presentation, according to the city's announcement and The Paper's write-up.

The city's Multi-Generational Recreation Center page has the project history and preliminary cost estimates. If you want to comment on which amenities should come first, The Paper points readers to the city's Governing Body page to reach their city councilor.

Andrea follows city projects like this one because they shape the north side of Rio Rancho over the coming years. If you live near Northern and Rockaway and want to talk about how the center's timeline fits your own plans for your home, Andrea Romero can walk through it with you. Get your free home valuation.

Work With Andrea

Andrea Romero brings local expertise and exceptional service to every client. Whether you're buying or selling in Albuquerque, she’s ready to guide you. Contact her today to get started!

Follow Me on Instagram